To search, type and hit enter.

Collett delivers Willenhall Super Grid Transformer

Collett Heavy Transport Deliver Willenhall Transformer

Collett delivers Willenhall Super Grid Transformer

Collet’s third girder bridge project in a four week period, this time the team were off to Willenhall Substation.

Having already delivered Cellarhead and Lovedean in the previous weeks, this would be the third of their August National Grid projects, and with the 170 Tonne transformer safely nestled in their girder bridge trailer they began the first 74 mile leg of the journey.

Under rolling escort from Cheshire, West Midlands and Staffordshire Police, their pre-planned route from the Port of Ellesmere saw them travel through Chester, Northwich, Stoke-on-Trent and Stafford before coming to rest in the abnormal load layby at Penkridge. There, the Team and the 66m (L) x 5.3m (W) x 4.8m (H) loaded combination would wait until the early hours of Sunday morning before continuing on, minimising disruption and impact on other road users in the more populated areas they were required to navigate.

Collett Undertake SPMT Transformer Operations

Working closely with Cheshire, Staffordshire, Wolverhampton and Walsall Councils in the pre-planning of the project, the Collett’s Team had already arranged for the removal of any street furniture, which identified in their specialist swept path analysis reports, would potentially impede the safe passage of the loaded combination. Another potential pinch point would be the access to the Substation site. With the access on Bilston Lane being a residential area they had already notified these residents in advance, as well as local media, to ensure that those living within the affected areas would be well aware of the project before its commencement. At this point there would also be parking restrictions in place and the implementation of a temporary road closure at the entrance to the Substation grounds.

As the early hours of Sunday dawned, the Team departed the layby to continue on the second, and final leg of the journey to Willenhall Substation. Travelling between 10-15mph throughout the route, their convoy steadily navigated the outskirts of Wolverhampton before heading through to the more confined streets of Willenhall. Due to the 66m length of the combination and the tightness of the turns on to the site, the Team were required to circumnavigate two roundabouts on their approach, allowing them to facilitate a left turn to the site road and deliver the cargo to its required destination.

Collett Transship from Girder Bridge to SPMT

In the early hours of Sunday morning, approximately four hours after departing from the abnormal load layby some 15 miles away, the cargo arrived safely on site. Due to the restricted access to the Substation the Team began transhipment operations to discharge the transformer from the girder bridge to an awaiting 6 axle SPMT, with an adapted operating speed to suit the axle loads. Once loaded, they hydraulically lowered the SPMT and the transformer to a height of 5.6m allowing the cargo to be driven on to the site before manoeuvring into storage position and lowering onto support stools.

With the jacking & skidding system already in place, the Heavy Lift Team began the process of gradually delivering the transformer to its final positioning. After lowering the transformer to the skid track, the hydraulic push pull units were engaged, extending and retracting between the locking points and effortlessly gliding the Super Grid Transformer to its designated plinth within the grounds of the Substation.

Collett Transport Jackin & Skidding Transformer

With the Super Grid Transformer safely skated into position that completed the hat-trick, Cellarhead, Lovedean and Willenhall all safely delivered and bringing to a close an extremely busy four weeks!

https://www.collett.co.uk

You may also like:

Safety comes first in heavy transport and lifting project in Singapore

ALE’s operational expertise and focus on safety has been demonstrated during the heavy transportation and lifting operations of an FPSO project ...

Marr Contracting awarded specialist heavy lifting contract

Australian-based heavy lifting tower crane specialists, Marr Contracting Pty Ltd (The Men From Marr’s), have been awarded the contract to deliver ...

ALE crane methodology saves significant costs on steel mill build

ALE’s in-house engineering team has used its expertise to save site costs and devise a lifting design that optimised the site during multiple ...

Announcement

HeavyTorque White Logo

It is with regret, that the HeavyTorque team have decided to take a stand based on an industry-wide ‘blind eye’ to the waste in the magazine and periodicals business.

HeavyTorque (#15, July 2018) was the final issue to grace the shop shelves, both on the High Street and across the travel network. As part of our onward strategy to adapt, HeavyTorque will now be distributed exclusively through controlled circulation and available through printed subscription.

Please note, this change will only affect newsstand purchasers. There will be no change for our loyal print subscribers.

Why the newsstand change? Quite simply, we can no longer (in good conscience) participate in a distribution programme that creates such an inherent waste of our precious natural resources – and money.

For those of you who have enjoyed HeavyTorque from the newsstand, we sincerely appreciate your business – and we would hope that you’ve enjoyed the magazine enough to consider a direct subscription?

Single Issues

If you prefer to purchase individual issues (one at a time), you will still have the ability to do so, both online (via the website), or by calling our offices +44 (0) 1572 3450872. Orders for single issues received before the pre-publication deadline will be mailed along with the subscribers.

Current and Back Issues

Our website also caters for those looking to purchase back issues. To browse Back Issue availability, follow this link: https://www.heavytorque.co.uk/shop/

Annual Subscription (UK/Europe and Rest of the World)

Never miss a beat, and keep up with every issue of the magazine via an annual subscription. To purchase your annual subscription, please visit: https://www.heavytorque.co.uk/subscribe/

It remains our objective, philosophy, and goal to provide our readers with the best content available, together with stunning feature photography. We do hope you will continue to support our venture!