To search, type and hit enter.

ALE deliver transformers using transhipment move through London

ALE deliver transformers using transhipment move through London

ALE was contracted to deliver three transformers weighing 135t and measuring 7.6m x 4.98m x 4.55m to the new National Grid substation in Highbury, North London. The delivery to site involved taking a route on the M25 motorway in one night, followed by a daytime move through London. Because of site restrictions, ALE needed to find tranship the transformer and required the road closure of the A1 at Holloway Road – a busy high street area in the Islington borough of London.

The transformers were transported from the vendor’s manufacturing facility in mainland Europe via the ports of Rotterdam, The Netherlands, and Tilbury, UK. Once the transformers arrived at the Port of Tilbury, all three transformers were offloaded by mobile crane from a coaster vessel.

Using ALE’s AL50 (14 axle) girder frame and 8 axle lines of SPT, along with two of ALE’s award-winning Trojan trucks, each transformer was transported individually: the first in October, the second in November and the third in January. Once at the road closure on Holloway Road, the transformers were offloaded from the girder frame and transhipped onto 8 axle lines of SPT to transport the transformers the short distance along Seven Sisters Road to the substation site, delivering the transformers in front of each foundation. This was all performed within the time permitted by the authorities.

Tom Irvine, Project Manager for ALE, said: “Right from the start, this transformer move was challenging as we had to find a route that was structurally capable and also a location close enough to the site to tranship the transformers from the girder frame trailer to a smaller trailer for the final delivery and positioning at the site. After working with multiple local authorities, our Logistics and Project Management teams found a suitable route and an agreement reached to offload the transformer and transfer it onto 8 axle lines of SPT at Holloway Road.

“The teams involved worked together to ensure that all three transformers were delivered safely and on schedule. By providing an innovative solution and through forward planning, we could successfully complete a complex transportation route through urban and residential areas of the Greater London area.”

Each transformer was delivered to site over two days. After delivery to the substation site, all three transformers have been installed by ALE onto their respective foundations using conventional jacking and skidding methods.

You may also like:

Denzai Group continues to expand with Goldhofer

Founded in 1968, Denzai Group is one of Japan’s leading heavy haulage companies and engineering service providers, with eleven national ...

A strong showing for Goldhofer at HeavyTorque LIVE!

Two 2500 tonne heavyweights for Silamas

The Thai transportation specialist Silamas, headquartered in Samuthprakan, owns more than 550 Goldhofer axle lines in its fleet and is one of the ...

ALE use unique skidding techniques for Korchagin topside in Russia

HTA Popup

Published in March 2018, this fantastic 220 page, A4 Landscape Yearbook, designed and published by HeavyTorque, reflects the continued growth, and achievements of the Heavy Transport Association (HTA). Printed full-colour throughout, this is a must-read for those with an interest in the heavy and specialist transportation sector – very much recognised as the ‘bible of the industry’.