To search, type and hit enter.

ALE deliver transformers using transhipment move through London

ALE deliver transformers using transhipment move through London

ALE was contracted to deliver three transformers weighing 135t and measuring 7.6m x 4.98m x 4.55m to the new National Grid substation in Highbury, North London. The delivery to site involved taking a route on the M25 motorway in one night, followed by a daytime move through London. Because of site restrictions, ALE needed to find tranship the transformer and required the road closure of the A1 at Holloway Road – a busy high street area in the Islington borough of London.

The transformers were transported from the vendor’s manufacturing facility in mainland Europe via the ports of Rotterdam, The Netherlands, and Tilbury, UK. Once the transformers arrived at the Port of Tilbury, all three transformers were offloaded by mobile crane from a coaster vessel.

Using ALE’s AL50 (14 axle) girder frame and 8 axle lines of SPT, along with two of ALE’s award-winning Trojan trucks, each transformer was transported individually: the first in October, the second in November and the third in January. Once at the road closure on Holloway Road, the transformers were offloaded from the girder frame and transhipped onto 8 axle lines of SPT to transport the transformers the short distance along Seven Sisters Road to the substation site, delivering the transformers in front of each foundation. This was all performed within the time permitted by the authorities.

Tom Irvine, Project Manager for ALE, said: “Right from the start, this transformer move was challenging as we had to find a route that was structurally capable and also a location close enough to the site to tranship the transformers from the girder frame trailer to a smaller trailer for the final delivery and positioning at the site. After working with multiple local authorities, our Logistics and Project Management teams found a suitable route and an agreement reached to offload the transformer and transfer it onto 8 axle lines of SPT at Holloway Road.

“The teams involved worked together to ensure that all three transformers were delivered safely and on schedule. By providing an innovative solution and through forward planning, we could successfully complete a complex transportation route through urban and residential areas of the Greater London area.”

Each transformer was delivered to site over two days. After delivery to the substation site, all three transformers have been installed by ALE onto their respective foundations using conventional jacking and skidding methods.

You may also like:

DAF Trucks opens new UK Headquarters

DAF Trucks UK held an official opening ceremony this week to celebrate its recent move to a new head office facility in Haddenham. The £20 ...

Mike Corcoran appointed Acting Managing Director for Volvo Trucks UK & Ireland

Mike Corcoran has been appointed Acting Managing Director Volvo Trucks UK & Ireland. He succeeds Arne Knaben, who takes up an appointment as ...

Jørn Bolding – Goldhofer’s man for Scandinavia for Forty years

In 1970 Jørn Bolding set up his own logistics business and has retained his passion for the transport industry to this day. Even at the age of ...

Bespoke Turnkey Solution aids the build of the RRS Sir David Attenborough polar research vessel

ALE has utilised its experienced team and in-house design expertise to complete the heavylifting activities for the RRS Sir David Attenborough ...

Announcement

HeavyTorque White Logo

It is with regret, that the HeavyTorque team have decided to take a stand based on an industry-wide ‘blind eye’ to the waste in the magazine and periodicals business.

HeavyTorque (#15, July 2018) was the final issue to grace the shop shelves, both on the High Street and across the travel network. As part of our onward strategy to adapt, HeavyTorque will now be distributed exclusively through controlled circulation and available through printed subscription.

Please note, this change will only affect newsstand purchasers. There will be no change for our loyal print subscribers.

Why the newsstand change? Quite simply, we can no longer (in good conscience) participate in a distribution programme that creates such an inherent waste of our precious natural resources – and money.

For those of you who have enjoyed HeavyTorque from the newsstand, we sincerely appreciate your business – and we would hope that you’ve enjoyed the magazine enough to consider a direct subscription?

Single Issues

If you prefer to purchase individual issues (one at a time), you will still have the ability to do so, both online (via the website), or by calling our offices +44 (0) 1572 3450872. Orders for single issues received before the pre-publication deadline will be mailed along with the subscribers.

Current and Back Issues

Our website also caters for those looking to purchase back issues. To browse Back Issue availability, follow this link: https://www.heavytorque.co.uk/shop/

Annual Subscription (UK/Europe and Rest of the World)

Never miss a beat, and keep up with every issue of the magazine via an annual subscription. To purchase your annual subscription, please visit: https://www.heavytorque.co.uk/subscribe/

It remains our objective, philosophy, and goal to provide our readers with the best content available, together with stunning feature photography. We do hope you will continue to support our venture!