To search, type and hit enter.

ALE Mega Jack performs first jack-up in Europe

ALE Mega Jack Performs First European Lift

ALE Mega Jack performs first jack-up in Europe

ALE has used the revolutionary Mega Jack system for the first time in Europe as part of the Albert Kanaal Project in Belgium.

The Mega Jack system, engineered to push structures of staggering weights and sizes, was utilised to jack-up the main bridge of a bridge heightening project in Genk, Belgium.

Jacking-up the bridge sections was the first phase of the project. The main bridge, with a span of 180m and weight of 4,500t, along with the two side bridges, weighing 536t each, were jacked-up 2.9m in three consecutive days. This enabled the client to adjust the foundations and finish other civil works over the following three weeks, before ALE jacked-down the main and the two side bridges on the adjusted foundations. Eventually, the height allowance of the bridge for ships to pass under was increased with 2.4m.

Jos Baelemans, Project Engineer, said: “One of the challenges was to utilise a computerised jacking system with a jacking accuracy of +/- 0.3mm and a read-out accuracy of +/- 0.01mm. Furthermore, as the bridge foundations were located close to the quayside, a system was required with a high jacking capacity and a small footprint.”

“Given the extreme weight of the bridge, we believe the optimum solution would be to use our Mega Jack System. This jacking system comprised of eight jacks, each with 1,300t capacity, thus creating a total lifting capacity of 10,400t. By using the Mega Jack, we could complete the jack-up quickly and safely within the space available.”

“For both side bridges, a computerised jacking system with a total of 2,000t capacity and oversized steel beams was used, which allowed for the bridge to be jacked-up on all 14 bearing points simultaneously”. The bridge heightening is part of the Albert Kanaal Project, in which over 50 bridges will eventually have a free passing height of 9.1m to allow ships with four layers of containers to pass through the channel. Some bridges need to be completely replaced, other bridges only need to be heightened and some bridges already have the sufficient height.

ALE has also been awarded the contract to launch the new bridge at Zolder, weighing approximately 1,200t. This bridge is also part of Albert Kanaal project and the launching will take place in the autumn of 2016.

You may also like:

Major addition to the fleet at Sea & Land Integrated Corp

Sea & Land Integrated Corp, with its headquarters in New Taipei City, Taiwan, is one of the country’s leading logistics service providers. ...

HC Wilson purchase new 4-axle Volvo FH540

Well-known industrial and plant fabrication carriers, H.C. Wilson Transport Ltd. of Suffolk has ordered its first new Volvo truck; a high ...

The Heavies 2020 – Friday 20th March 2020

BIGGER, BETTER AND BACK: THE HEAVIES 2020 AT PETERBOROUGH ARENA While much of modern life seems confusing in the extreme and the uncertainty over ...

New Volvo FH for UK Lift & Haul

FORS Gold-accredited UK Lift & Haul of Rochford, Essex, has put a new Volvo FH-500 6×2 tractor unit with pusher axle into operation, ...