To search, type and hit enter.

Collett & Sons transformer tasks

Collett Deliver Cellarhead Substation Transformer

Collett & Sons transformer tasks

_______

AS PART OF THE NATIONAL GRID’S SUBSTATION UPGRADE PROGRAMME, COLLETT UNDERTOOK THE TRANSPORTATION OF SUPER GRID TRANSFORMERS USING A SCHEUERLE GIRDER BRIDGE.
_______

Following the delivery of a super grid transformer to Cellarhead Substation, Stoke-on-Trent, Collett’s Projects and Heavy Lift Team journeyed south to transport a 169-tonne super grid transformer from Portsmouth International Port to Lovedean Substation, Waterlooville, north of the city. The project was completed over a three-week period in August 2018.

Collett undertook the pre-planning works, the unloading of the transformer from the vessel at the Port through to its final delivery to the substation. As with Cellarhead, it included on-site offloading and installation using hydraulic jacking and skidding equipment.

Swept path analysis reports of the route identified pinch-points where modification would be needed to allow the 66m-long, 5.3m-wide loaded girder bridge to complete the journey. This was particularly evident at the beginning of the route throughout the residential areas of Twyford Avenue and Northern Parade. Collett liaised with local councils and constabularies to implement parking restrictions to allow the free movement of the girder-bridge convoy.

Once discharged from the vessel and loaded onto the Scheuerle girder bridge, the 169-tonne transformer began its 12-mile journey to the substation. Across Portsmouth, Cosham, Havant, Purbrook, Waterlooville and Horndean, the convoy travelled under police escort. As with the previous Cellarhead project, two ‘end-change’ operations had to be completed along the route effectively flipping the combination 180º to allow for onward transport, arriving safely at the Lovedean National Grid Substation early in the afternoon.

On arrival, on-site restrictions did not allow the direct movement of the transformer to its plinth. Collett used a multi-directional system to skid the transformer over the bund wall onto a steel platform. Once situated on the platform the hydraulic skidding system was then turned through a 90º angle to complete the positioning.

Once the transformer was positioned, Collett transported the 10 40ft containers of ancillaries required for the project, each of which arrived at Southampton.

You may also like:

Safety comes first in heavy transport and lifting project in Singapore

ALE’s operational expertise and focus on safety has been demonstrated during the heavy transportation and lifting operations of an FPSO project ...

Marr Contracting awarded specialist heavy lifting contract

Australian-based heavy lifting tower crane specialists, Marr Contracting Pty Ltd (The Men From Marr’s), have been awarded the contract to deliver ...

ALE crane methodology saves significant costs on steel mill build

ALE’s in-house engineering team has used its expertise to save site costs and devise a lifting design that optimised the site during multiple ...

Announcement

HeavyTorque White Logo

It is with regret, that the HeavyTorque team have decided to take a stand based on an industry-wide ‘blind eye’ to the waste in the magazine and periodicals business.

HeavyTorque (#15, July 2018) was the final issue to grace the shop shelves, both on the High Street and across the travel network. As part of our onward strategy to adapt, HeavyTorque will now be distributed exclusively through controlled circulation and available through printed subscription.

Please note, this change will only affect newsstand purchasers. There will be no change for our loyal print subscribers.

Why the newsstand change? Quite simply, we can no longer (in good conscience) participate in a distribution programme that creates such an inherent waste of our precious natural resources – and money.

For those of you who have enjoyed HeavyTorque from the newsstand, we sincerely appreciate your business – and we would hope that you’ve enjoyed the magazine enough to consider a direct subscription?

Single Issues

If you prefer to purchase individual issues (one at a time), you will still have the ability to do so, both online (via the website), or by calling our offices +44 (0) 1572 3450872. Orders for single issues received before the pre-publication deadline will be mailed along with the subscribers.

Current and Back Issues

Our website also caters for those looking to purchase back issues. To browse Back Issue availability, follow this link: https://www.heavytorque.co.uk/shop/

Annual Subscription (UK/Europe and Rest of the World)

Never miss a beat, and keep up with every issue of the magazine via an annual subscription. To purchase your annual subscription, please visit: https://www.heavytorque.co.uk/subscribe/

It remains our objective, philosophy, and goal to provide our readers with the best content available, together with stunning feature photography. We do hope you will continue to support our venture!