Mammoet builds on expertise in the Americas to execute a time-saving concept for one of the biggest mining companies in the world

Mammoet Complete First Australian Dragline Project

Mammoet builds on expertise in the Americas to execute a time-saving concept for one of the biggest mining companies in the world

Mammoet has completed its first dragline relocation project in Australia. The dragline, weighing 2990 metric tons, was jacked up and transported 99 kilometres on SPMTs overcoming a variety of obstacles on the way. Using experience from similar projects in the USA, Mammoet’s team safely completed the project within the deadline – saving weeks of time it would have taken for the dragline to move there using its own propulsion (‘walking’) mechanism.

“We were very well supported by the wider Mammoet community out of Singapore and the USA. Their technical expertise coupled with the experienced SPMT operators from Australia and Malaysia is instrumental to their success.” Tom Graham, Project Manager, CPB Contractors.

CPB Contractors, a wholly owned subsidiary of Australian publicly listed company CIMIC Group Limited, were contracted to move the Marion 8050 dragline. CPB undertook all civil works and engaged Mammoet as the jacking and transport contractor for the relocation. The goal was to move the dragline from one mine to another in the coal mining Isaac Region, of Queensland, Australia, in the most efficient and economical way possible.

Prior to the transport, extensive route surveys had identified numerous challenges on the route such as a 9.5% incline and 10.0% declines, seven river and creek crossings, three railway crossings and two highway crossings. The railway crossings presented a significant potential risk to the project schedule as there was only one 24 hour window each month when the rail lines were shut down for planned maintenance, allowing the dragline operation to cross.

Ground conditions threatened the tight timescale for the operation to cross the first railway. By working around the clock, the Mammoet team made it on time for the scheduled crossing. Making all essential milestones ensured the dragline was delivered to its destination on time. This significantly reduced the downtime for this essential piece of mining equipment. Mammoet’s expertise ensured the project was safely engineered and executed – setting a new standard for dragline transport in Australia.

“We were genuinely very impressed by Mammoet’s engineering expertise and their hands-on approach.” Tom Graham, Project Manager, CPB Contractors.

You may also like:

Major addition to the fleet at Sea & Land Integrated Corp

Sea & Land Integrated Corp, with its headquarters in New Taipei City, Taiwan, is one of the country’s leading logistics service providers. ...

HC Wilson purchase new 4-axle Volvo FH540

Well-known industrial and plant fabrication carriers, H.C. Wilson Transport Ltd. of Suffolk has ordered its first new Volvo truck; a high ...

The Heavies 2020 – Friday 20th March 2020

BIGGER, BETTER AND BACK: THE HEAVIES 2020 AT PETERBOROUGH ARENA While much of modern life seems confusing in the extreme and the uncertainty over ...

New Volvo FH for UK Lift & Haul

FORS Gold-accredited UK Lift & Haul of Rochford, Essex, has put a new Volvo FH-500 6×2 tractor unit with pusher axle into operation, ...